Working resource
Recovery exercise record
A blank record for planning and documenting a recovery exercise on one service, so the result can be trusted by the people who will rely on it.
Free to use and adapt · No registration · Print or copy the sections you need
How to use it
Agree the scenario, scope and success criteria with the service owner before the exercise, and fill in the remaining sections as it runs. The record is complete when someone who was not there can tell what was tested, what worked, what did not and who is doing what next.
Read what a recovery test actually demonstrates for the reasoning behind each section.
1. Service and scenario
Scope of the exercise| Item | Agreed answer |
|---|
| Service | |
|---|
| Scenario (what has been lost or damaged) | |
|---|
| Recovery time objective, and who agreed it | |
|---|
| Recovery point objective (acceptable data loss), and who agreed it | |
|---|
| Environment used for the exercise | |
|---|
| What must not be touched | |
|---|
2. People and roles
Who took part| Role | Name or team | Responsibility during the exercise |
|---|
| | |
| | |
| | |
| | |
| | |
3. Timeline
Record times as they happen, not afterwards.
Exercise timeline| Time | Step | Who | Result or note |
|---|
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
4. Proof that the service works
Evidence of recovery| Check | Result |
|---|
| Agreed user task, and who performed it | |
|---|
| Did the task succeed? | |
|---|
| Most recent data available after recovery | |
|---|
| Data loss compared with the recovery point objective | |
|---|
| Elapsed time compared with the recovery time objective | |
|---|
5. Dependencies met along the way
Identity, keys and secrets, DNS, network access, licences and suppliers are where recoveries usually stall.
Dependencies| Dependency | What happened | Was it documented? |
|---|
| | |
| | |
| | |
| | |
| | |
6. Gaps and actions
Follow-up actions| Gap found | Action | Owner | Due by |
|---|
| | | |
| | | |
| | | |
| | | |
| | | |
7. Decision
Service owner decision| Item | Answer |
|---|
| Is the recovery approach accepted as it stands? | |
|---|
| Conditions or limits on that acceptance | |
|---|
| Date of the next exercise | |
|---|
| Signed off by | |
|---|